1.
Preparation before starting the pump
(1) Remove
the useless stuffs from the pump clean up the site.
(2) Fill
adequate amount of lubricating
pump oil.
(3) Before
connecting coupling, check the steering direction of the motor to see if the
pump is consistent with the direction of rotation, after verification, connect
couplings.
(4) Before
the coupling is installed, use hand to move the shaft, which should be flexible
rotating. (5) Before starting the pump, it should be filled with the delivering
liquid, in order to get rid of the air, then the discharge pipe valve should be
closed.
(6) When
transporting hot oil, before transporting, the pump should be preheating, which
is carried out by use of hot
oil pump continuously being transporting. Its pump casing temperature
should not lower than the inlet oil temperature 40 ℃. Preheated rate of 50 ℃ / hr.
Former multistage ring section pump begins to warm up, you should press the
segment, pump bracket, two side nuts right amount released, preheat and then
tighten it.
(7) Check
foundation bolts, and the lubricating oil and cooling water supply situation.
2. On
Starting the pump
(1) A
thorough examination of all the preparatory work is already perfect.
(2) Open
the various instruments of the switch, turn off the pressure gauge cocks.
(3) Turn
on the power supply or the starter motor when the pump reaches the normal
speed, and the corresponding pressure after the meter pointed out, gradually
open the discharge line valve, and adjust to the desired conditions. In the
case of the discharge line closed, continuous working time of the pump can’t
exceed 3 minutes.
(4) In the
process, we should always pay attention to the vibration of the motor and pump
power readings, the number of vibrations should not be more than 0.06 mm.
3.
Maintenance
(1) Check
bearing fever economic situation, bearing temperature should not exceed a
temperature of standard values, and always check the oil level and oil ring,
the regular replacement of oil.
(2) Do not
use the suction valve to regulate the flow, to avoid cavitation.
(3) The
pump should not be less than the design flow in the case of continuous
operation at 30%, if you must run continuously under these conditions, you
should install a bypass pipe at the outlet, the excess traffic access to the
pump inlet tubing.
(4) The
constant attention to seal leakage and heat conditions.
(5) Always
check for loose bolt, rotor pump
inlet temperature and the temperature is consistent, vibration export gauge
fluctuations and pumps.
(6) Note
that the pump is running without noise, such as found in the abnormal state,
promptly notify the person concerned staff.
4. Stop
The Pump
(1)
Gradually close the discharge line valve.
(2) Power
off (or stop the turbine)
(3) After
the pump to cool, and then turn off the cooling system and seal each pipeline
oil.
(4) The
liquid and the cooling water pump should be empty and cleaning in case of
cracking and bonding.